In determining incentives, use _____ as a guide.

Prepare for the DBIA Exam 2 with targeted quizzes. Use flashcards, multiple-choice questions, and detailed explanations to master Design-Build principles. Elevate your exam readiness!

Multiple Choice

In determining incentives, use _____ as a guide.

Explanation:
In design-build, incentives are most effective when they push the project toward reducing the uncertainties that could derail cost, schedule, and quality. Using risk as a guide means crafting rewards and penalties around actions that mitigate or eliminate the major risks to the project. For example, incentivizing early coordination between design and construction teams, proactive risk mitigation planning, or securing long-lead items early directly targets areas where unknowns could cause delays or cost overruns. When the incentive structure focuses on risk reduction, the contractor is encouraged to address the uncertainties up front, which improves predictability and overall project value for both owner and builder. Relying solely on schedule or cost targets can lead to behaviors that ignore underlying risks (like rushing work to hit a milestone or cutting corners to save money), whereas tying incentives to risk encourages decisions that stabilize the entire project.

In design-build, incentives are most effective when they push the project toward reducing the uncertainties that could derail cost, schedule, and quality. Using risk as a guide means crafting rewards and penalties around actions that mitigate or eliminate the major risks to the project. For example, incentivizing early coordination between design and construction teams, proactive risk mitigation planning, or securing long-lead items early directly targets areas where unknowns could cause delays or cost overruns. When the incentive structure focuses on risk reduction, the contractor is encouraged to address the uncertainties up front, which improves predictability and overall project value for both owner and builder.

Relying solely on schedule or cost targets can lead to behaviors that ignore underlying risks (like rushing work to hit a milestone or cutting corners to save money), whereas tying incentives to risk encourages decisions that stabilize the entire project.