Change orders are bilateral agreements.

Prepare for the DBIA Exam 2 with targeted quizzes. Use flashcards, multiple-choice questions, and detailed explanations to master Design-Build principles. Elevate your exam readiness!

Multiple Choice

Change orders are bilateral agreements.

Explanation:
Change orders are bilateral agreements to modify the contract. When a change in scope, cost, or schedule is needed, both owner and contractor must negotiate and sign a change order that amends the contract terms. This ensures that neither side unilaterally alters the agreement and that all adjustments—such as new scope, price, milestones, or delivery dates—are mutually agreed and documented. Note that a construction change directive can be issued unilaterally to direct a change before agreement, but it becomes a change order only when both parties sign off on the revised terms. So, the statement that change orders are bilateral agreements is correct.

Change orders are bilateral agreements to modify the contract. When a change in scope, cost, or schedule is needed, both owner and contractor must negotiate and sign a change order that amends the contract terms. This ensures that neither side unilaterally alters the agreement and that all adjustments—such as new scope, price, milestones, or delivery dates—are mutually agreed and documented. Note that a construction change directive can be issued unilaterally to direct a change before agreement, but it becomes a change order only when both parties sign off on the revised terms. So, the statement that change orders are bilateral agreements is correct.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy